5000 cubic meter per day Persian Gulf seawater RO desalination plant handover procedure successfully finished. Process and potable water production has been continuing over the design capacity.

Cartridge filter prior to SWRO section

Cartridge filter prior to SWRO section

Handover follows on from project completion which is the point in the construction, commissioning, and start up when the project manager determines that the project is, to all intents and purposes, complete and ready for the client operation. Once completion has been certified, the contractor gives up occupation of the site to the client who takes over responsibility for operation, security, insurance, and maintenance. 