Successful FAT process completion for four sets Ex-type offshore packages

Successful FAT process completion for four sets Ex-type offshore packages

Four “Sanitary Treatment Packages” have gone through several performance tests in the presence of Third Party Inspector as well as the project’s client representatives.

Sanitary package FAT completion

Sanitary package FAT completion

All FAT results were completely satisfactory. Noteworthy tests which were performed are as follows:

1.      “Control Panels” performance & response in:

a.       Manual & Automatic Modes.

b.      Timing & priorities signals.

c.       Alarms & restrictions.

d.      Equipment emergency shut downs & total package shut downs.

2.      “Air Blowers”, “Macerator Progressive Cavity Pumps” & “Metering Pumps” performance.

3.      “Pressure Safety Valves (PSVs)” response to over pressure & assuring of their set points performance to protect the system from damages.

4.      “Pressure Regulating Valves” performance.

5.      “Level Switches” performance & signals.

6.      “Solenoid Valves” performance.

7.      Mixing condition inside the “Accumulation Tank” while diffusers were in service.

8.      All remaining instrumentations such as “Rotameters” & “Pressure Gauges” response.

Afterwards, the “Release Notes” were issued by third party inspector and the packages were ready for packing & marking procedure and the final inspection.